Once again, a follow-up regarding availability... steel for construction does not seem to be the problem (according to our shell builder)... the actual problem (for us) is bricks (Poroton), which are no longer available at all. According to him, all construction sites are listed and are now being processed step by step... no one can say when we will receive our bricks.
Another point out of interest: Has anyone recently ordered a brine heat pump including deep drilling or received an offer?
We are installing a brine-water heat pump with surface collectors (deep drilling was not possible due to the water protection area). The heat pump is the Bosch Compress 7800i LWM. It is expected to arrive soon but has been ordered for a long time. The same applies to the Bosch controlled residential ventilation with enthalpy heat exchanger. I cannot say anything about the price, as construction is being done with a general contractor and payment is made in installments.