Construction costs are currently skyrocketing

  • Erstellt am 2021-04-23 10:46:58

Pinkiponk

2021-07-31 16:22:54
  • #1
My husband and I probably made a mistake in the contract or did not consider something due to lack of time: We hadn’t had a sampling yet, thus no construction plan either. The fixed price was only set for 18 months, after that the total price increases by 0.4% per month, but only for a maximum of 6 months. After that, the price list valid at the time of acceptance applies. :-( Well, in the worst case, we just have to pay the 5% to get out of the contract again, because the price at the time of acceptance in the next (worst case the following) year is likely to be unrealistic. We have to take the blame for the construction permit taking longer than expected; the other side is responsible for it taking months until a sampling appointment and that it was not possible to get a sampling appointment before the construction permit was granted.
 

Hausbau0815

2021-07-31 17:50:41
  • #2
In newer contracts, there is usually a clause stating that material price increases above x % result in price adjustments. I also know that construction companies for wooden houses pay their customers 25,000 € if they withdraw from the contract. In the case of a price increase of 100,000 €, the contractor cannot, in my opinion, insist on compliance with the contract nor demand a withdrawal fee, since the cause does not lie with the client. My limit for the contractor to insist on contract compliance would be an increase of 10 %, as is generally possible with craftsmen's invoices.
 

Hausbau0815

2021-07-31 17:56:21
  • #3


One can only hope that all this will balance out again. The question is, if you cancel this contract, what then? Building with someone else probably won’t be any cheaper. And if you give it up entirely, you’ll have to pay the bank a lot for the unused loan. And that would be for nothing. Not a good solution either.
 

DaSch17

2021-07-31 23:14:58
  • #4


I've heard that too. Even sums around 50,000 EUR…
 

DaSch17

2021-07-31 23:19:09
  • #5


Why do you want to get out of the contract? Do you no longer want to build after all?
 

ypg

2021-07-31 23:54:14
  • #6
Huh? That wasn’t doable? Why not?
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben