Allthewayup
2022-08-03 15:07:43
- #1
I had promised to inform you once the pricing round with the GU was completed. For understanding: the offer from October 2021 was approximately €510,000 turnkey without ancillary construction costs. As of today: approximately €520,000. Mainly responsible for this are reinforcement steel, windows, bricks, insulation materials, and a few other materials in total. We will receive a detailed list of the deltas by email.
To our surprise, some items have even become cheaper (front door ~ €600, sanitary 2k) but this has to be attributed to discount effects.
So our "worst-case scenario" (€40k) is fortunately still far away. The start of construction has also been confirmed for 10 weeks from now. Until the start of construction, no significant price increases are expected as most of it is already ordered or en route to the warehouse by then. Except, of course, JIT material.
We will now try to save the remaining buffer beyond the construction project in order to be able to make special repayments immediately after completion.
To our surprise, some items have even become cheaper (front door ~ €600, sanitary 2k) but this has to be attributed to discount effects.
So our "worst-case scenario" (€40k) is fortunately still far away. The start of construction has also been confirmed for 10 weeks from now. Until the start of construction, no significant price increases are expected as most of it is already ordered or en route to the warehouse by then. Except, of course, JIT material.
We will now try to save the remaining buffer beyond the construction project in order to be able to make special repayments immediately after completion.