Completion date in General Contractor Agreement - Wording assistance

  • Erstellt am 2019-05-28 21:26:09

goalkeeper

2019-05-29 10:39:36
  • #1


I meant the clause more or less like this:

“As the date of readiness for occupancy, October 31, 2020 at the latest is agreed, but only if the plot is buildable by October 1, 2019 at the latest. Otherwise, the readiness for occupancy shall apply 10 months after the building permit is granted and completion after 12 months.”

I only want to express that it must be completed in 2020 if the plot is indeed buildable by October 2019. And this buildability was communicated to me both by our building authority and the site manager of the development company.

Our general contractor simply should not dawdle if they could actually start building. That’s what it’s about for us. We understand that he has no influence on the completion of the development work.

I should probably have expressed myself more clearly.
 

Zaba12

2019-05-29 10:45:21
  • #2
I know what you mean, but the GC also only employs subs. If they can’t or don’t want to, nothing happens. And it is never the GC who dawdles but his subs, the weather, construction technical problems, or issues with the client or neighbors. Therefore, there will also be no guaranteed construction period until XX.XX.XXXX.
 

Frank Hartung

2019-05-29 10:51:27
  • #3
A guaranteed construction period down to the exact point will not work. The question is also what should happen if the contractor does not meet this construction period. Have you thought about that as well? Because in fact, the claims for damages are capped even then. So just writing "We will be finished on xx.xx.2020" is pretty boring to begin with.
 

goalkeeper

2019-05-29 10:53:29
  • #4


But your argument doesn’t fit – since the new construction contract law, a duration or a guaranteed construction time must be included.

In our general contractor contract it states that it will be ready to move in 10 months after the start of construction and completely finished after 12 months. And the start of construction is one month after the building permit is granted. Therefore, he or his subs cannot take their time during the construction period.

He can only delay the building permit by submitting it later. But once he has it, he must step on the gas.
 

cschiko

2019-05-29 10:56:30
  • #5
Well, if the [GU] already had these 10 or 12 months stated in the contract on their own accord, then it might be possible to adjust this accordingly. However, if at all, they will probably only agree to something like construction start no later than x months after the prerequisites for the construction start are fulfilled and then completion by, for example, 31.10.2020.

However, the problem remains that the [GU] can only really plan you in once everything is in place. Therefore, I would first try to have a conversation to see to what extent they will allow something to be written into the contract. The problem is what happens if they plan you in with construction start on 31.10.2019, but the development, surveying, or something else is still not available? Therefore, they will probably only plan you in and fix this in the contract only when everything is fixed.
 

ypg

2019-05-29 10:58:45
  • #6
I would personally focus more on the word "bezugsfertig". Because what does it mean in reverse? A commissioning, that is, taking possession, means the silent acceptance of the house. Completely without an official protocol, without a list of defects.
 

Similar topics
13.09.2012Feeling pressured into a contract, is that normal?17
22.09.2012Who else fell for a contract with a reservation clause? - Search13
09.04.2014Questions/neglected plot/meadow, determining construction measures44
06.01.2015First buy the plot, then calmly plan and build...?11
02.06.2016Necessary insurances during construction and afterwards11
12.09.2022Terminate house contract before expiry - withdrawal clause/property25
10.09.2016Construction financing and contract with the developer24
16.09.2016False information about the property in the exposé39
16.01.2017No building permit as long as the land is not developed?10
10.05.2017Transfer of property from mother-in-law to me and my wife41
05.09.2017Finance land/house separately - fixed interest rate11
22.01.2018Building on still foreign land - Waiting for building permit25
10.03.2019Purchased land after demolition, construction debris in the ground34
09.09.2022Experiences with forest conversion in the context of building permits in Brandenburg20
22.12.2019Crane from the neighbor on my property67
03.03.2021Single-family house + land (purchase or leasehold) with high interest rates26
24.11.2021Plot of land in sight - looking for tips, tricks, suggestions39
09.07.2021Is the construction time specified in the prefabricated house contract binding?19
30.03.2022Terminate the contract with the general contractor "early"22

Oben