stephan.l
2019-05-16 18:06:11
- #1
:
All explanatory texts regarding the invoices below are not shortened but complete. I dare to say that this is therefore not verifiable? The dates are correct, there was a delay – thanks to the building authority – the amounts include VAT.
1st invoice, 10/2016, €6,200
"planning services provided so far, preliminary draft"
2nd architect invoice, 11/2016, €10,000
"design planning, approval planning"
3rd invoice 01/2018, €10,000
"planning services provided so far, ½ detailed design"
4th architect invoice, 03/2018, €9,000
"structural planning (static calculation)" (according to the HOAI 2013 contract, this was explicitly not to be commissioned by him, but directly by me)
5th architect invoice, 05/2018, €9,200
"object planning part 3, building and interiors"
6th architect invoice, 05/2018, €10,000
"structural planning (static calculation), including execution planning"
"technical building equipment (heating-ventilation-sanitary), including execution planning" (I have received no documents whatsoever regarding the last point, nothing)
Construction stop 06/2018 – 12/2018, legal fees for me €21,000
7th architect invoice, 04/2019, €10,000 - unpaid
"Architect according to contract 2.1.1 – 2.1.9 proportionally (funny, phase 9 is not commissioned at all according to the contract)
"Travel expenses according to contract 6.2 proportionally" (also funny, he verbally promised me zero and indicated zero in his cost estimate)
Yes, for point 7 I then pulled the emergency brake. Until the construction stop (clearly the responsibility of the architect, but not legally clearly attributable to him), I was probably a bit trusting. After that, no longer. The reference specifically related to the fact that it is a very, very difficult building authority, and he supposedly could handle it well. Now they no longer talk to him.
All explanatory texts regarding the invoices below are not shortened but complete. I dare to say that this is therefore not verifiable? The dates are correct, there was a delay – thanks to the building authority – the amounts include VAT.
1st invoice, 10/2016, €6,200
"planning services provided so far, preliminary draft"
2nd architect invoice, 11/2016, €10,000
"design planning, approval planning"
3rd invoice 01/2018, €10,000
"planning services provided so far, ½ detailed design"
4th architect invoice, 03/2018, €9,000
"structural planning (static calculation)" (according to the HOAI 2013 contract, this was explicitly not to be commissioned by him, but directly by me)
5th architect invoice, 05/2018, €9,200
"object planning part 3, building and interiors"
6th architect invoice, 05/2018, €10,000
"structural planning (static calculation), including execution planning"
"technical building equipment (heating-ventilation-sanitary), including execution planning" (I have received no documents whatsoever regarding the last point, nothing)
Construction stop 06/2018 – 12/2018, legal fees for me €21,000
7th architect invoice, 04/2019, €10,000 - unpaid
"Architect according to contract 2.1.1 – 2.1.9 proportionally (funny, phase 9 is not commissioned at all according to the contract)
"Travel expenses according to contract 6.2 proportionally" (also funny, he verbally promised me zero and indicated zero in his cost estimate)
Yes, for point 7 I then pulled the emergency brake. Until the construction stop (clearly the responsibility of the architect, but not legally clearly attributable to him), I was probably a bit trusting. After that, no longer. The reference specifically related to the fact that it is a very, very difficult building authority, and he supposedly could handle it well. Now they no longer talk to him.