MadameP
2019-09-19 11:38:49
- #1
Curious how different the order can be. For us, the roof is already covered and the windows are already in. But only now is the electrician at work and the installer will start shortly.
That was actually planned that way for us, too. But since the windows were so massively delayed, we decided to start with the rough installations already so that we don't lose endless time.