Final sprint:
This week, the ventilation system, electricity meter, and hot water boiler were installed. Heating/plumbing/ventilation is thus finished, electrical work is ongoing, but the electrician will have to come back after moving in to do some work in the kitchen, put the ventilation into operation, and wire the door station + Ekey.
The bus system is also working exactly as desired. Roller shutters / blinds worked right away. The long training time for KNX has really paid off by now. Especially my wife is very impressed and no less glad that I managed to get it all done. She had major concerns about this, after all ^^
The roof terrace is also finished; I took advantage of the nice weather to install the lamps.
The access path + carport was also filled up and compacted. That’s enough for this year; next year we will pave it.
Over the weekend, we will still paint the main bathroom and the base area in the technical room.
Then we can set up the sanitary fixtures and shelves there so that everything is ready for moving in.
On Monday the kitchen will be installed, and the carpenter will start with the stairs.
Right now everything is going well again, but it has to be, after all, we want to move in in 2 weeks