Something is finally happening here as well.
- Cellar and manure pit filled in
- Foundations (eh, there are none, just built directly on rock) of the old wall secured with concrete
- New retaining wall was supposed to be poured this week, but won’t happen, the crane is still at another construction site
- Excavation is gone
- Scaffold is up
- Sewage and such are being laid
- Construction power available
- Crane platform filled with mineral mix
- Floor slab insulation delivered
The solid wood walls are coming in week 39.