House Pictures Chat Corner - Show off your house pictures!

  • Erstellt am 2015-11-25 10:27:31

Müllerin

2019-03-16 12:33:15
  • #1
With us, it took 11 months including the base slab until moving in, of which 4 weeks nothing happened because it was too cold and 4 weeks probably due to delays, no idea. It was okay that way.
 

hemali2003

2019-03-16 12:40:21
  • #2


I see it differently. We were living in the house 6 months after the first groundbreaking – solid construction. Drying times were only for the foundation slab and screed, and those were fully observed. And that was regular screed, not anhydride (is that what it’s called?). And our house is super dry.

We built with an affordable general contractor, but our construction supervisor had no quality objections. Although he is rather a critic of this cheap chain. Nothing worth mentioning went wrong.

Of course, there weren’t any great idle times – most of the time it was about a week, I believe.
 

11ant

2019-03-16 18:18:53
  • #3

Almost: Anhydrite.
 

KingSong

2019-03-16 18:28:16
  • #4
So we had about 7 months with timber frame construction from earthworks to moving in... and that with 285m². If the contractor hadn’t dawdled so much, 6 months would have easily been possible. We had a concrete slab, screed, and drywall that needed to dry. To be fair, it should also be mentioned that about 8 months passed from signing the contract to the earthworks.
 

Nordlys

2019-03-16 20:54:18
  • #5
15.3. to 1.9. exactly five and a half. However, they had already done the base slab before Christmas in December and left it to cure until March. Construction method Ytong plastered, classic. The house was sufficiently dry at the time of moving in,
 

Lobster

2019-03-17 09:03:33
  • #6
We have been in since the end of February. The start was on May 1, 2018 - makes 10 months. Classic Yong/KS construction method with brick facing without a basement. If the municipal utilities hadn’t slept and we had gotten through the in-house work a bit faster towards the end, it could have been 8-9 months. But that wasn’t necessary either, so all good
 

Similar topics
21.10.2011Floor slab insulation "Yes!" or "No!"14
18.09.2012Construction of a base slab with frost skirt but without foundation10
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
14.09.2012House financing - house, garage, and foundation slab approx. 290,000 EUR11
26.10.2012External perimeter insulation floor slab, basement mold risk11
21.11.2013Is the floor slab still possible this year?15
15.07.2014Foundation slab for Danwood bungalow? Company for complete works?11
23.11.2014Stone throw on foundation slab - builder's liability insurance?16
15.06.2015Base slab or strip foundations for garage12
07.09.2015Minimum distance from the base plate?11
11.09.2016Base plate - construction/insulation etc. - experiences please!10
05.08.2016Leave the floor slab over winter15
20.08.2016Base slab vs strip foundation15
13.09.2016Insulation under the floor slab EPS or XPS?12
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
06.10.2016Base plate with defects?22
27.11.2016Double insulation below and above the floor slab?10
22.07.2017Horizontal sealing of the base slab24
20.02.2017Dimensions of the base plate do not match25
13.01.2025Insulating wooden floor panel with straw20

Oben