The craftsmen are hardworking, so are we:
- The painters are painting the upper floor and ground floor. Actually, also the chimney in glitter-gray. The nice thing is, the paint/paste is washable when wet.
- We painted the basement over the weekend. Only the storage cellar room is left.
- The tiler has been working since yesterday and is preparing everything. He will start with the walls.
- Next week, the floors in the ground and upper floors will be tiled. The basement will come later, the screed is not dry yet.
- The roof hatch was installed yesterday.
- The blinds arrived today and will be installed in the next few days.
- The front door will arrive in 2 weeks.
- The staircase will be more expensive because natural beech laminated board, lacquered does not match the wood tile. It will now have to be oak. The quality will be decided by the surcharge.