My wife would also like such large stones as a slope.
What should you roughly expect to pay for something like that?
@Topic:
Our drywall installer was here and did the boxing out for the kitchen cabinet wall and the wall to the dressing room.
The tiler is now also at work and is doing the wall tiles in the bathrooms.
The floor tiles are now expected to arrive in calendar week 43, which makes completion in calendar week 48 realistic again.
The painter has meanwhile sanded down the ceilings and sanded the walls, next week he will start painting the ceilings, then I can already install the spots + presence detectors there.
Since Monday, the electrician has been working on the control cabinet and is wiring everything on terminal strips. In the meantime, I have prepared the KNX actuators and assigned all the physical addresses everywhere. That way I can program everything directly with the laptop afterwards.
Now it’s really getting down to the nitty-gritty with the bus system, I’m as happy as a little kid