The shell construction is now nearing completion.
Currently, the parapet and ring beam are being constructed on the main roof. The parapet of the roof terrace is already finished, and the anteroom is being built there, on which a monopitch roof will be installed.
Last week, the window fitter came to take measurements; he assured us that everything will be installed within 4-5 weeks.
In the meantime, heating/plumbing/electrical rough installations are to take place so that plastering can then begin promptly.
In our opinion, the masons were not quite as productive in the last two weeks as hoped, but this is by no means a criticism considering the heat that had to be endured recently.