The parquet layer started with the 4 bedrooms yesterday and was finished at 3 pm today. Now that's what I call an achievement. On Thursday, all doors will be hung, the electrical work will be completed over the weekend, and the bathrooms next week.
Moving in and relocating will be on 12.07. (on my birthday :rolleyes .
Thus, half of the basement will still be tiled during ongoing operations and the stair steps will be installed on 29.07. or painted 3 days prior.
The pictures are not really exciting but progress is progress.
Pictures:
- Bedroom of No. 2, from yesterday without baseboard
- Kitchen lighting. The kitchen unit will also get the same lighting.
- We will make a railing around the terrace from flat steel powder-coated in anthracite and stainless steel cables (for safety reasons), because it will partially drop 1.7m down. Something like this just mounted on the L-stones. The dimensions have already been taken. It's just under 17m.