Last week the exterior plaster was applied here. After some discussions, the screed will be installed on Wednesday. Everything looks good for the planned move-in just before Christmas.
let's see who gets in first [emoji6]
The move-in was actually planned for week 48/49, but we still have massive delivery problems with the floor tiles.
Otherwise, everything is going quite well, but without the floor it’s not so nice.
On Thursday there was infrastructure work, the heating is currently being installed, and the painter is diligently filling the ceilings.