A little update:
- Windows have been measured and ordered. Installation will take place in January.
- Stairs have been measured.
- On Friday, the ceiling elements will be installed. Electrical work and ventilation will also be prepared in the upper floor ceiling.
- On Monday, the upper floor ceiling will be poured.
- On Tuesday, the roof will be supported.
- Rough installation of plumbing and electrical will take place in January.
It’s hard to believe, although we only started with the L-blocks on 16.10., everyone kept their word that the shell construction will be weather-tight by Christmas. Crazy.