Did you just pay it anyway? Or did you wait?
If I wait until the services are completed (in 1.5 weeks), I will be in default of payment. (?)
I yelled at the site manager about what went wrong, he then immediately contacted me by phone and said that we would receive a corrected construction progress report next week.
Payment will only be made once the items invoiced are actually completed. Of course, there will be no money before that.