Build a terraced end house with an additional unit (GÜ) on your own

  • Erstellt am 2019-05-27 10:48:59

goalkeeper

2019-06-03 14:56:41
  • #1


The middle house has to be built set back because it needs to have two parking spaces, and there is only room for those in front of the house. We, on the other hand, place our two parking spaces beside the house.

We don’t actually find it that bad – everyone can build individually here and doesn’t have to pay the high premiums charged by developers. It can be somewhat tedious at times – but because of the staggered construction, our terraced house stands “free” and therefore it feels a bit like a small single-family home.

That’s also why we have been planning since January, so we can start as soon as the development area opens. Since everyone builds their own terraced house here, it will get pretty tight later on with all the cranes needed. As it currently looks, we will be the first ones.
 

11ant

2019-06-03 19:38:59
  • #2

I have the feeling there has already been a change (?)



That’s exactly the problem: in informational events this attitude is repeatedly expressed by interested parties, and the municipalities then “learn” from this to make this very same mess again at the next opportunity. They don’t mean it badly, they just want to be re-elected ,-)


It is precisely this crane logistics cacophony that causes a plot to remain undeveloped in the end.
Uncoordinated construction management was sometimes possible when 500 sqm and up were the standard plot size, but today this overwhelms even Pronto Salvatore and experienced stocking machine programmers.

As much as I usually hope to be wrong with my doomsaying, here there are reasons that unfortunately are increasingly obvious even to laypeople :-(


I hope the legislator was less naïve here: just imagine if the deadline for the last entitled party to request underpinning had to expire before anyone in the construction area could start.
 

Escroda

2019-06-04 08:11:52
  • #3

I find the neighbor law clear – in NRW even somewhat more detailed with deadline specification. The builder informs the neighbor that he wants to erect a boundary wall and the neighbor has two months to consider whether to assert claims regarding the foundation execution.
If the transfer of possession has not taken place by the deadline and the seller has not asserted any claims, construction can be started at the builder’s discretion.
The underpinning request only comes into play when the building application has been submitted or the house already stands. In the first case, the builder could still kindly adjust the plan; once the slab has been poured, however, it’s too late.
Since the timing coordination of the various construction projects by individual builders usually does not succeed – as we also see here – I also consider it impossible that a first builder without a basement can prevent the second builder from having a basement. The second builder will always be able to rely on the neighbor law.
 

goalkeeper

2019-06-04 08:25:33
  • #4
According to the building authority, we will be named the next candidate(s) very soon. Then we will see if the neighbor also wants a basement. However, since the other corner house is building a basement, he would be throwing money away twice if he didn’t build one. He would have to do a deep foundation himself there.

Assuming we can actually start in October, according to the general contractor, one could wait up to three weeks before the start of construction with the structural analysis and thus also with the decision on the deep foundation.

Therefore, we are optimistic that the issue will be resolved in about three months or that a buyer will be firmly decided by then.
 

Escroda

2019-06-04 09:46:28
  • #5

..., but the neighbor would have to pay for it if they have not yet submitted a building application.
 

goalkeeper

2019-06-04 10:09:39
  • #6


The corner house will also be built with a basement very soon. Therefore, the middle house would then have to underpin our floor slab and the other corner house would have to have deeper foundations if the middle house does not want a basement.
 

Similar topics
05.06.2010Basement made of high perforated bricks or concrete?11
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
26.10.2012External perimeter insulation floor slab, basement mold risk11
09.06.2013Costs of earthworks without basement15
01.07.2013Additional insulation in the Ytong basement (36 cm)14
09.04.2015Sacrifice the basement for 20m² more living space?15
10.08.2015In which season of the year is it best to bring screed into the basement10
06.10.2015Correct formulation for a waterproof basement11
24.10.2015Built without a basement & regretted?77
08.12.2015uninsulated basement = wet basement?20
17.02.2016KFW 55 in semi-heated basement - cold basement31
20.08.2016Base slab vs strip foundation15
28.06.2017Basement costs - Is the floor slab offset?17
15.03.2018When is a slope a slope? Basement vs. slab19
14.03.2018Slight slope, building with a basement or a floor slab?16
03.03.2018Price difference between ground slab and basement. Can it be estimated?32
14.10.2019Dampness in the basement on the floor slab and walls25
11.01.2021Basement or slab? - Cost estimation24
22.09.2022Basement without additional flooring / cleaning floor slab34
03.03.2024Basement or ground slab: which is more sensible for the property situation?55

Oben