Right on time for tomorrow's handover, after today's heavy rain one spot in the dormer is soaking wet again. ops:

So laying the flooring on Wednesday is probably off for now - my beautiful schedule.
 

lastdrop

2020-05-11 20:51:22
  • #2
Be glad that it poured down like that today ... good test
 

halmi

2020-05-11 21:00:58
  • #3
Water got in there before, right? What was done about it?
 

goalkeeper

2020-05-11 21:03:58
  • #4
Back then, something came in through a sheet of the dormer. That would only become completely sealed with the plastering. Back then, the carpenter had fiddled around with some sealing tape on the sheet.
 

Winniefred

2020-05-11 21:05:22
  • #5
Somehow I saw coming that this would still occupy you. Hopefully it can still be fixed well. But don’t let yourself be brushed off so easily again with a simple explanation.
 

halmi

2020-05-11 21:13:14
  • #6
That should be without plaster as well. I would have a professional take a closer look at it.
 