And how is everything else in the house?
So far everything is going wonderfully. The tiler is almost done, the staircase has been in since last week, the painter still has about two days of work. The bathrooms still need the textured paint and some white here and there. The drywall installer did the storage room today.
The painter's fleece looks absolutely great on the "pimped" Q2 wall. The blue wall in the children's room looks much cooler in reality.
Currently, the sanitary equipment and the installation of the ventilation system are still missing. But all of that will happen this week.
Otherwise, next week on Monday the front door will be installed and on May 7th the handover – on the 13th then the exterior plastering.