Build a terraced end house with an additional unit (GÜ) on your own

  • Erstellt am 2019-05-27 10:48:59

bortel

2020-01-22 15:04:46
  • #1
that sounds reasonable. Or a staircase made of pallets, not pretty... but it works for now.
 

Climbee

2020-01-22 15:32:07
  • #2
I also mean: as parking spaces, a compacted area is sufficient at first so that two cars can be parked on one's own property. I like the idea of the pallet staircase, and otherwise I would also wait until at least the basement of the middle house is finished and filled up. Even if the dear wife already has garden dreams – I would find it too much of a waste of money to pay for an interim solution first and then do the final solution when it’s finally possible.

I would still have an appointment reserved with the landscaping contractor – otherwise it might become tight. Best to coordinate with the middle house owner if they have a schedule, and ask when the basement is supposed to be finished and when it will be filled, and then attach your own appointment to that.
 

cschiko

2020-01-22 15:32:22
  • #3
I would also rather go with the option of stairs going down, because piling up is likely to be difficult as long as nothing is happening next door. An alternative would be a "Balcony," that is, a 1.50m high platform. But setting that up securely is more complicated and more expensive than the stairs option.
 

11ant

2020-01-22 15:57:08
  • #4
Here clearly no. As you write it, this applies on the one hand universally – but on the other hand only for all the zero-eight-fifteens, where during the provisional period there is a bumpy track – but this one almost at the appropriate finished height – lying there. Then the cars temporarily stand 8cm of paving stone thickness plus substructure lower than finished. In this concrete case, however, at least L-beams and other protections against the viscosity of a one-and-a-half-meter-high rain-soaked mass of earth must be installed so that the cars do not slide away on an avalanche (or like over a collapsed mine). That is already a different matter – also with regard to the nonchalance potential
 

Scout

2020-01-22 16:00:11
  • #5
In a worst-case scenario, you can also park the car on the street in front or nearby until the neighbor has secured his earthworks project.
 

guckuck2

2020-01-22 17:31:18
  • #6


No offense, but how many new housing developments have you already lived in?
I can tell you from experience that people like for everyone to build at the same time and then immediately work on the outdoor facilities, but no one can guarantee that.

For example, we ourselves had to wait for an adjacent neighbor. I could have put up the fence alone, but then I would have had to pay for it completely myself, and if he wanted to put a garage on the boundary, we would probably have had to redo it. So you leave it alone, or at least we do.

You can also construct a temporary path to the front door, and that has nothing to do with the boundary design. There is also nothing against completing the earthworks entirely; you just slope the last half meter lightly and wait to see how the neighbor positions himself. You can still go ahead with the terrace, etc. That’s how we did it and have seen it many times in the housing development and among friends.
As a rule, road construction also comes afterwards, but no one is deterred from creating a driveway. It gets adjusted again during or after the road construction, and then the job is done.
 

Similar topics
06.01.2015Where to place the staircase? Attic conversion hip-roof bungalow19
08.01.2018Stairs in the hallway, the floor plan is actually already done :o(20
07.03.2015What should be considered when designing stairs / differences in the winding?22
26.06.2015Floor plan question, stairs, window, orientation12
27.08.20152 full floors, passage to garage, utility room under stairs25
11.12.2015Question about floor plan, especially stairs13
15.02.2016necessary staircase23
02.05.2016Staircase floor plan design, tread and stringer21
12.07.2016Floor plan question, garage, stairs33
15.08.2016Technical room as small as possible - under the stairs?10
15.09.2016Stairs delivered without a railing and now I have to pay extra?19
15.01.2017Which staircase did you take?77
16.02.2017Straight staircase - why?14
06.03.2017Finishing staircase - parquet28
29.03.2017Construction defect - Staircase not in order12
24.02.2020Stairs - Are the stair dimensions 2.00x2.00m okay?68
17.10.2017Single-family house approx. 150 sqm floor plan - How to plan the staircase?65
24.09.2018City villa with straight staircase, open modern design, 140m²18
02.07.2018Stairs in the living room as a hype - Pros & Cons?26
22.10.2018Tiles on a half-spiral staircase - who has experience with that?38

Oben