Today there is a lot going on at the construction site again. In addition, the weather is great. The utility company came with 4 vehicles. ops: Water is already connected. Electricity is currently being connected to the line.
The gas line on the property and the connection in the house are in place. Only the connection to the main line is still taking some time. We will be connected to a larger supply line. Since its protection no longer looks good, a part will be replaced. For this, a bypass will be created first so that the other consumers won’t be without gas. At least we can now sand the pipes and close the trenches on the property.