- #1
The recent period has been somewhat stressful. The ceiling installation is quite far advanced. Lamps are being installed. APs (indoors) are almost all in place. Paint is also finished except for the stairwell. This is only primed. It will only be fully painted when we do the final touch-ups. There have been some rescheduling of appointments. Some appointments cannot be rescheduled. The result is that next week we will have a "full house." On Monday, the facade builder will start installing the aluminum Cobond panels, the pool builder is coming, we will sand the floor on one level, the utility provider is finally delivering the electricity meter, the electricians will be there, as well as the ceiling installers and the plasterer (pavilion)... The rest of the glass installation is supposed to begin on 06.07. Keep your fingers crossed that it goes reasonably as planned.