rick2018
2020-02-09 08:44:04
- #1
At the end of this week, we were finally able to put up the retaining wall to the neighbor.
This will be filled from both sides.
At the beginning of the week, it was too windy, so it was postponed.
Since we had to lift the parts over the house and partly across the entire property, heavy equipment was needed.
It ended up being a 220-ton mobile crane
If the weather is good, the entire walls will be backfilled next week.
Inside, the HVAC installation continues. Drywall partitions are also partly up. The electrician has to come first here before we can finish sheathing them.
The garage door is already installed as well.
Overall, things are going quite well. At the end of February, progress will slow down a bit due to Fasnet.
This will be filled from both sides.
At the beginning of the week, it was too windy, so it was postponed.
Since we had to lift the parts over the house and partly across the entire property, heavy equipment was needed.
It ended up being a 220-ton mobile crane
If the weather is good, the entire walls will be backfilled next week.
Inside, the HVAC installation continues. Drywall partitions are also partly up. The electrician has to come first here before we can finish sheathing them.
The garage door is already installed as well.
Overall, things are going quite well. At the end of February, progress will slow down a bit due to Fasnet.