Floor plan planning shortly before submitting the building application

  • Erstellt am 2017-10-02 23:25:16

ypg

2018-05-15 08:06:46
  • #1


That's just how it can be! Building something is a bit more complex than car repair, which can also sometimes take disproportionately longer. Always stay calm.

I consider October unhealthy.
 

niri09

2018-05-15 08:31:23
  • #2
October also seems very unrealistic to me. We are at about the same stage, but with a smaller house, and are planning to move in at the end of December or beginning of January.
 

haydee

2018-05-15 09:05:21
  • #3
With us, it took 4.5 months from roofing to installing windows, all sanitary and electrical installations, insulation, exterior plaster, etc., up to the floor coverings. A fast-drying screed was installed, which was ready for covering after 2 weeks. It couldn't have gone much faster. The companies and craftsmen also knew each other and had worked together several times before.
 

R.Hotzenplotz

2018-05-15 12:10:14
  • #4


That was tentatively planned. But I don't believe in it.
 

niri09

2018-05-15 12:49:33
  • #5
Is it stated like that in the contract?
 

R.Hotzenplotz

2018-05-15 14:03:39
  • #6


The contract states a construction period of months. You have to deduct a bit of frost time, but that doesn't leave much leeway. For the period after the nine months, a compensation amount has been contractually agreed upon in advance. So they are indeed under considerable pressure.

However, it wasn't that I pressured them to finish within nine months. Rather, they said from the beginning that the construction period is nine months, and I only negotiated which compensation would be payable if the nine months are not met.

Today the earthworker called me. Really, really bad. Nobody told him that a garage will be built to the left of the house. And he also doesn't understand why someone would commission a plate load test on topsoil. It might become an interesting liability question as to who has to bear which additional costs. Earthworks are unfortunately a separate trade. But the general contractor will be paid extra via an addendum contract for assuming construction management regarding the earthworks. And if he then doesn't inform the company where what needs to be carried out, I see him as responsible somewhere in this.

It's a shame; it started off so well but now the problems are piling up.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
04.11.2017Work contract with general contractor - questions about the offer37
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
13.07.2020Developer does not want to offset lump-sum damages with installments19
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
23.07.2021Earthworks... Dispute with the occupational disability insurance20
19.03.2023Consumer construction contract, construction contract not executed - compensation for damages?44
06.06.2023Estimation of construction time for the new build of a semi-detached house17

Oben