Floor plan planning shortly before submitting the building application

  • Erstellt am 2017-10-02 23:25:16

R.Hotzenplotz

2018-10-03 11:08:09
  • #1
The construction manager has been on sick leave for what feels like the fifth time since construction began. The drywall installer doesn’t know when he’s supposed to install the gypsum board ceiling, the roofer says the Velux ceiling spotlights should only have been installed after the gypsum board ceiling was in place, but they are already installed now. One of the spotlights is positioned so that it is blocked by a rafter in the roof and can’t be channeled at all. He doesn’t know what to do. Pure chaos! And they’re getting paid a five-figure amount for such construction management. Just messed up!

At least the plasterers thoroughly reworked every plaster that the construction manager had approved as okay. So purely goodwill that everything was okay.

After the bumpy blower door test, the drywall installer, according to his own statement, has already had to dismantle the covings in the bathrooms for the third time because something still needed to be sealed or the whole thing had to be documented with photos.

The base coat plaster is currently underway. In 10 days, the finishing plaster is supposed to be applied outside. The scaffolding is supposed to be removed in three weeks.

The screed is being heated. However, various pipes in the underfloor heating circuit are cold. I don’t get it. But at the moment, I can’t ask anyone. The exposed pipes in the recessed screed of the showers also seem not to be carrying any water. Nevertheless, it’s moderately warm inside the place.
 

Snowy36

2018-10-03 11:43:40
  • #2
I feel for you.......I had to fire our site manager.....now we continue on our own......

Chin up!
 

blackm88

2018-10-03 12:19:13
  • #3
Isn't the underfloor heating system filled and checked for leaks before the screed? Then the screed is applied and then the heating is turned on?
 

Caidori

2018-10-03 13:41:59
  • #4
If done correctly, the underfloor heating is tested for tightness before the screed, with us this would be done by pressure. After the screed, it makes no sense, as you can no longer access it then.
 

Bookstar

2018-10-03 19:18:38
  • #5
As with the water pipes, a leak test is performed before the screed is installed. There is also a protocol for this.
 

Josephine2489

2018-10-04 09:06:04
  • #6


Possibly this was not done, and it seems a bit mocking to me to write like this here.

It is not the first time in this thread that other users write "Shouldn't have...", "It should have...", "It is self-evident..."

But on this construction site, not much is taken for granted, and the line between "well-intentioned" and "You are doing (everything) wrong" is very thin here.

I only feel sorry for the builder now and I wish him a good outcome despite everything... :-(
 

Similar topics
29.02.2012What can be detected in a blower door test, which house values?18
13.08.2014Underfloor heating grooving - experiences?19
10.05.2015Screed uneven - defect removal refused52
27.05.2016Plastic fittings/water pipes and insulating underfloor heating beneath screed?40
07.08.2016Upper floor without screed - only concrete floor15
08.06.2016Questions about underfloor heating - new subfloor/screed/granite tiles14
11.01.2019Underfloor heating in the shower?14
29.03.2018Having underfloor heating milled in afterwards. Experiences!!!13
25.01.2017Blower Door Test for KfW 70 according to the 2012 standard?15
27.12.2017Underfloor heating heating demand with at least 60 mm screed30
07.02.2020Blower Door Test - Meaning of the Result35
03.02.2019Underfloor heating in the floor slab - advantages and disadvantages?15
19.12.2019Blower Door Test 1.7 with two hints22
09.02.2022Floor plan single-family house OWL approx. 150 sqm with east garden175
01.03.2020Protective pipe for underfloor heating forgotten in the area of movement joints39
13.05.2020Self-adhesive vinyl on screed20
10.02.2022Screed heating program incorrectly set and heating coil loosened18
25.11.2022Mill underfloor heating or apply new screed?17
28.07.2023Screed has been in for three days and is still wet?52
02.10.2024Underfloor heating on the ground floor: insulate or not?16

Oben