R.Hotzenplotz
2018-10-03 11:08:09
- #1
The construction manager has been on sick leave for what feels like the fifth time since construction began. The drywall installer doesn’t know when he’s supposed to install the gypsum board ceiling, the roofer says the Velux ceiling spotlights should only have been installed after the gypsum board ceiling was in place, but they are already installed now. One of the spotlights is positioned so that it is blocked by a rafter in the roof and can’t be channeled at all. He doesn’t know what to do. Pure chaos! And they’re getting paid a five-figure amount for such construction management. Just messed up!
At least the plasterers thoroughly reworked every plaster that the construction manager had approved as okay. So purely goodwill that everything was okay.
After the bumpy blower door test, the drywall installer, according to his own statement, has already had to dismantle the covings in the bathrooms for the third time because something still needed to be sealed or the whole thing had to be documented with photos.
The base coat plaster is currently underway. In 10 days, the finishing plaster is supposed to be applied outside. The scaffolding is supposed to be removed in three weeks.
The screed is being heated. However, various pipes in the underfloor heating circuit are cold. I don’t get it. But at the moment, I can’t ask anyone. The exposed pipes in the recessed screed of the showers also seem not to be carrying any water. Nevertheless, it’s moderately warm inside the place.
At least the plasterers thoroughly reworked every plaster that the construction manager had approved as okay. So purely goodwill that everything was okay.
After the bumpy blower door test, the drywall installer, according to his own statement, has already had to dismantle the covings in the bathrooms for the third time because something still needed to be sealed or the whole thing had to be documented with photos.
The base coat plaster is currently underway. In 10 days, the finishing plaster is supposed to be applied outside. The scaffolding is supposed to be removed in three weeks.
The screed is being heated. However, various pipes in the underfloor heating circuit are cold. I don’t get it. But at the moment, I can’t ask anyone. The exposed pipes in the recessed screed of the showers also seem not to be carrying any water. Nevertheless, it’s moderately warm inside the place.