Floor plan planning shortly before submitting the building application

  • Erstellt am 2017-10-02 23:25:16

R.Hotzenplotz

2018-07-10 18:07:10
  • #1


I already wrote that. He says he is aware that he deviated from the DIN standard but he builds 90% of the houses that way. Reason: The drainage is simpler.

However, the expert says his method of execution is neither equivalent nor considered state of the art. So why should I accept an inferior execution?
 

11ant

2018-07-10 19:08:11
  • #2
Without counting the commas, the report reads to me with the tenor "defects criticized, plaque assigned." I do not see 199 instead of 201 cm as a disputable deviation; with a 201 rough opening, I would have even expected 198 cm element height. So for me, the question is not why 199 instead of 201, but: why 201 instead of 213.

I think the structural engineer will be benched by the general contractor for a season, but the selling value of the house will not suffer measurable damage from the deviations.

I see your legal chances as largely dependent on the interaction between the expert and the lawyer.
 

R.Hotzenplotz

2018-07-10 19:15:52
  • #3


So you find the base sealing acceptable and think it should continue like this? The expert clearly stated that they need to address it again. The execution was substandard, it was not in my interest, and it simply was not agreed upon. Your assessment therefore confuses me a bit.



The contract simply states window height 201 cm and not window for a rough construction height of 201 cm. Basically, apart from that, I see it as you do, that the 201 cm window height as such is the problem. And the expert did try to point out a way to hold the architect liable in his statements. But the expert cannot show anything further; everything else goes into legal matters and we will clarify that tomorrow. However, if suddenly the threshold is 5 cm higher than stated, that is already a significant deviation. After all, the contract specifies 15 cm. Accordingly, from my point of view, new doors have to be installed anyway. And if new doors have to be installed, you can surely negotiate about getting other dimensions for an additional cost. There is certainly room for negotiation, also concerning the delay. The question is whether the building permit even allows the installation of taller (and ideally wider in the bedroom and bathroom) balcony doors.

Expert and lawyer have contact from other projects. That fits well.

The masonry will be exciting. I cannot imagine that the brick manufacturer will agree to grant such an approval. And we will not grant it either, as the expert writes. That is currently apparently the smallest issue, but it may be almost the hardest to solve because no one wants to grant the corresponding approval and the general contractor is not allowed to simply make such changes.
 

11ant

2018-07-10 20:02:59
  • #4
No, it just sounds to me that the expert's statement is less dramatic than expected from the last pages of this discussion. It essentially sounds repairable, although in this case ultimately without profit for the general contractor on this object. But that is probably "normal" tuition fees for testing a new shell builder.
 

R.Hotzenplotz

2018-07-10 20:08:24
  • #5


Oh, I see. On the last pages, it was more about the fact that the encapsulations are so massively disturbing. But that is less a problem of the expert and more – if at all – a legal problem. I will raise the issue tomorrow but I don’t expect much from it. Basically, we only have the encapsulation in the kitchen and the left office left. The right office has already been eliminated, and I will eliminate Child 1 through the use of the pipe ventilator.



I would like to start with a question. Assuming the general contractor is willing to correct the base sealing; how should one imagine that? Does the entire basement wall around the building have to be exposed? If yes, how are they supposed to do that in the garage area?
 

Snowy36

2018-07-10 21:55:07
  • #6


Yay, then my tip really helped!
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
04.11.2012Expert despite TÜV approval?13
01.10.2013Construction company would rather not have an assessor11
04.07.2015House contract with financing condition, lawyer wanted10
07.05.2015Have the work contract checked by a professional37
14.12.2015Expert discovers defects in the basement. What to do?11
04.07.2016Building without a contract - Concerns?39
30.06.2016Existing property - appraiser, financing, negotiating...17
01.08.2018Construction company demands extra costs due to cooperation with appraiser21
21.07.2020Lawyer wanted to sue the construction company52
11.04.2020Construction law - hire a lawyer or not yet16
01.11.2020Rough cost estimate house renovation built in '73 - appraiser17
20.10.2021Renovation of a 1960s house: Questionable expert recommendations?92
17.03.2022DSL Bank takes a long time processing, now also sending surveyors for 200k22
07.05.2023Is it sensible for the expert to inspect the base plate?55
28.06.2024Building permit - is a lawyer useful?12

Oben