Above all, they want to make it easy for themselves to meet the nine-month construction period. However, they only manage this because the self-performed trades are excluded. But the nine months would also have to be achieved if everything was included there. It will be a case for the lawyer to accurately quantify the exact days of the delay that can be finally applied there.
The general contractor is out: construction time is always counted without EL.