Hey,
it's me again :-) Wanted to give you an update :cool: So far, almost everything is running smoothly. There are two problems, rather challenges.
1. Unfortunately, we didn't know that the front door had to be installed with the windows. Nothing was mentioned in the construction plan, so we only ordered it externally about a month ago and it will arrive at the beginning of June. Therefore, the exterior plaster and also the screed could not be finalized.
2. During the exterior plastering, the plasterers' hose burst and the plaster stained the roof as well as the neighbor's brick facade. This will probably be covered by the plasterers' insurance and professionally cleaned.
Currently, final pipework for the sanitary facilities, heating, and electricity is being installed, underfloor heating can be laid from the beginning of May, and the screed will be poured the following week.
Photovoltaic modules (13.26 kWp) are also already installed.


it's me again :-) Wanted to give you an update :cool: So far, almost everything is running smoothly. There are two problems, rather challenges.
1. Unfortunately, we didn't know that the front door had to be installed with the windows. Nothing was mentioned in the construction plan, so we only ordered it externally about a month ago and it will arrive at the beginning of June. Therefore, the exterior plaster and also the screed could not be finalized.
2. During the exterior plastering, the plasterers' hose burst and the plaster stained the roof as well as the neighbor's brick facade. This will probably be covered by the plasterers' insurance and professionally cleaned.
Currently, final pipework for the sanitary facilities, heating, and electricity is being installed, underfloor heating can be laid from the beginning of May, and the screed will be poured the following week.
Photovoltaic modules (13.26 kWp) are also already installed.