Something positive for a change. The front door will finally be installed on Friday. The pipes for the ventilation system will also be laid. The following week, the drywall construction will take place.
The warm-up phase has been over since yesterday. 6,000 KW/h are on the meter. That’s nearly €2,000. I had planned for that. What’s clear is that there will be more due to additional work :cool: Finally no more emptying the construction dryer and airing out 2-3 times a day :-) But it had an advantage, you had time to take a very close look at the house :cool:
Today, the installation of the ducts for the controlled residential ventilation system has begun.
A question regarding registration at the house. We now assume that we will move in during August or rather September. However, we would like to send our daughter to the new school from the new school year (end of August). For this, registration in the village is necessary. Is it possible, for example, that my wife can already register with the child at the house address so that the child can attend the school in the new year? Or is there anything to consider in this regard?