Interior work continues. Since Tuesday, the screed is officially dry and the drying units and the heating cartridge have been turned off *HURRAY*
The drywall installer is in the house :cool:
From Monday, the flat plate collectors, the drainage system, as well as the garden connections for electricity and water will be installed. On Thursday, the Telekom connection will be set up.
In about 2.5 weeks, the tiler is supposed to come and from 08/09 the exterior plaster including the columns will be finished.
According to the Bosch sales representative, the ventilation system should arrive at the end of the month (non-binding). There is no delivery time yet for the geothermal heat pump. So the handover of the house will be decided by this.