Construction of a 144 sqm bungalow in Fichtenwalde (near Potsdam)

  • Erstellt am 2021-05-16 18:56:12

Tom1978

2021-11-29 18:11:47
  • #1
It continues. Fine staking completed. Foundation work included. Tomorrow the strip footings will arrive.


 

In der Ruine

2021-11-29 18:22:10
  • #2
Isn't there any civil engineering for a frost skirt? How deep do the strip footings go?
 

Tom1978

2021-11-29 18:39:48
  • #3


This is how it should look (more words)
 

Tolentino

2021-11-29 22:56:41
  • #4
Probably additives are added there. Then the reaction during setting is still a bit warmer. It even works down to -5°C.
 

Tom1978

2021-11-30 05:32:25
  • #5


Yes. I spoke with the earthworks contractor. Down to -5 degrees is no problem. There will be insulating mats on top, so the heat released by the concrete remains.
 

Tom1978

2021-12-01 18:09:35
  • #6
The foundation slab will be poured on Friday. Icke am looking forward to it :cool:


 