I have just taken another look at the timeline: The comparison was closed on 19.09.2019. It soon became clear that GU1 would not comply with it. On 17.12.2019, Anwalt1 filed an application for enforcement and advance payment of nearly €130,000 in additional completion costs at the district court.
On 15.01.2020, there was supposed to be a construction progress and defect assessment on site with the participants GU1 and his lawyer, myself, and our construction consultant. Of course, GU1 did not show up. His lawyer informed us that GU1 had sold the company, which was now called xyz Bauunternehmung, and a representative of the new company would come to the appointment, which did not happen.
On 20.01.2020, GU1's lawyer requested an extension from the district court for the deadline expiring on 20.01.2020 for a statement by three weeks until and including 10.02.2020, which was granted. On 10.02.2020, GU1's lawyer informed that she had withdrawn her mandate.
On 12.02.2020, the district court of Leipzig issued the order that the company xyz has to pay us €129,062.00 as an advance payment.
When RA1 conveyed this information to me and I did not burst into jubilation, he said he had expected a bit more enthusiasm. I wonder why. We both knew by then that this was now worthless.
Now comes this bill. After a year!
Looking at the sequence of events now, as I have gone through the documents again, I get so angry. We have been completely fooled here.