Construction progress: Duplex with WU basement and developed attic

  • Erstellt am 2021-01-04 14:44:59

Hausbau0815

2021-01-09 07:13:50
  • #1
After being absolutely frustrated yesterday evening, I did a bit of "reflection," not on myself, but on the matter itself, and came to the conclusion that things cannot continue like this. Since GU2 let the 3rd and final deadline for a decision expire yesterday and instead his lawyer informed me by email that GU2 had commissioned him to provide a statement, but for technical reasons he could not send it to me (which I do not understand), my patience ran out and I informed GU2 that I now only accept the termination. Then I located my architect from 20 years ago and arranged an appointment with her for Sunday.
 

Uhu2207

2021-01-09 12:33:53
  • #2
Hello hausbau0815,

I am absolutely speechless.... I wish your family all the best and lots of unity. The time will come when this whole thing ends. I’m keeping my fingers crossed for you.

I built in BaWü and awarded the trades individually with an external site manager. In hindsight, that was the best decision. We took the craftsmen who have made a name for themselves over the years through good work. Of course, I had to pay well for that. When I think about how I got upset over little things and read your case... I feel a bit ashamed.

Again, all the very best...

Best regards
 

Wolkensieben

2021-01-10 15:12:53
  • #3
Great. Check it off, get up, straighten your crown and keep going.
 

Hausbau0815

2021-01-11 19:15:55
  • #4
I met with the architect yesterday. She was somewhat irritated or rather shocked by what she saw and said she needed to let it sink in first. On Friday, I had written to GU2 that I would now only accept the contract termination since he had let the third deadline pass. I was all the more surprised today when he showed up at the construction site as if nothing had happened. We were just in the process of checking or correcting the ceiling insulation between the upper floor and the attic. What came towards us in the process, words fail me, see photo. This has nothing to do with construction defects anymore. For me, this is property damage and sabotage.
 

Trademark

2021-01-11 21:44:31
  • #5
Does the GU comment on the deadlines? Or is he dragging this out even further now?
 

Hausbau0815

2021-01-11 21:47:12
  • #6
He completely ignores that. Today I sent his lawyer a comprehensive letter.
 

Similar topics
04.07.2015House contract with financing condition, lawyer wanted10
21.07.2020Lawyer wanted to sue the construction company52
11.04.2020Construction law - hire a lawyer or not yet16
28.06.2024Building permit - is a lawyer useful?12

Oben