Hausbau0815
2021-01-04 14:44:59
- #1
Due to several inquiries, I will try to provide a summary of the construction progress so far:
Purchase of the plot in 2013
Signing of the construction contract with GU1 from the Leipzig surroundings: 16.05.2018
Semi-detached house with WU basement and finished attic
Basement: 200 sqm living space. Both semi-detached halves together just under 400 sqm
no own contributions, without painting and flooring, except tiles
guaranteed fixed lump sum price: €490,000
The plan was for my daughter and her family to move into one side of the semi-detached house and my son with his partner on the other side
In contact with GU1 since 2015, also visited several houses built by him and spoke with the builders, no major problems
Construction start: 08.10.2018
Basement excavation 1,200 m³ soil, disposal costs: €18,000 extra
later it was found that at least 500 m³ were removed unnecessarily, which were hauled back free of charge, but no reimbursement of disposal costs. It was claimed that I had wanted the removal even though I cried after every truck.
Several visits by BG Bau and imposition of a two-time construction halt because the excavation did not have the required slope, thereafter a huge construction pit was excavated, which completely sacrificed the already paid construction road.
After the completion of the ground floor (international masonry brigade without authorization for concrete and masonry work), an email arrived stating that due to static requirements, additional costs of €1,000 would be incurred. We accepted that. One day later, a new email came saying that Mr. GU had miscalculated because he forgot a beam and it was now over €6,000. We then disagreed, referring to the "guaranteed fixed lump sum price."
At the same time, it became apparent that the entire house protruded at least 12 cm higher out of the ground than planned, which was visible due to the light shafts suspended in the air, which were actually supposed to be integrated into the future parking spaces. This was initially vehemently denied. Another point was the filling and compaction of the excavation pit. According to the soil report (which the GU had), the excavation material was not suitable for refilling as it was not compactable. Nevertheless, it was used and not even compacted. This resulted in the ground giving way and the scaffolding leaning against the shell construction. Furthermore, our basement was larger than planned, which in itself would not have been bad if the ground floor above had been adjusted accordingly. The design initially did not provide for external insulation at the basement. However, at contract signing there was supposed to be 10 cm. This was apparently not passed on to the planner. Contract signing including external insulation 16.05.2018, planning documents apparently without external insulation: 18.06.2018?????
After pouring the ground floor ceiling in December, work stopped = construction stop imposed by the GU. Meanwhile, I had engaged an external construction consultant. On 17.12.2018 crisis meeting in GU’s office. At this time the invoice for the ceiling amounting to €47,500 had not been paid yet. We agreed on immediate transfer of €40,000 to the GU and withholding €7,500 until defect clarification under the condition that work would continue from calendar week 2.
Instead of continuation, all equipment and materials were removed in calendar week 2, and the scaffolding was dismantled by the end of January. The GU was unreachable. My construction consultant recommended a lawyer who then filed a lawsuit for continuation of construction in March.
In the meantime, we had commissioned an expert to determine defects, who identified defects amounting to €31,000. Thus, the GU was significantly overpaid.
From May 2018, various settlement offers went back and forth without agreement.
When in July I found out by internet research that Mr. GU had founded a second construction company, I was at my wit's end because I realized what this was heading toward. I was so desperate at some point that I called the GU’s wife (a phone number was given to me by another victim who still plays a special role here; let’s call him Mr. X) and asked her to influence her husband. She said she knew nothing about any of this. Less than 10 minutes later, I received a call from my lawyer that the GU’s lawyer had complained to him. Shortly thereafter I received a cease and desist claim and was supposed to pay €1,000. My lawyer said he could not represent me in that matter. Mr. X (as said, another victim, but not as a builder, rather as a contractor) then put me in touch with his lawyer who got me out of that situation very well.
The trial date was set for 04.10.2019. One week before, the GU entered into a settlement with us, in which we actually came out quite well. He had to pay the court and lawyer fees (totaling nearly €30,000) and damages (about €17,000). We only had to cover the settlement costs. By the settlement, he committed to completing the house by 30.11.2019. However, this date was totally unrealistic. Apart from the fact that he only resumed construction in mid-October. After the roof truss was put on (it was by then end of November and we were still miles away from completion), work stopped again.
Everything went through the lawyers again. In December 2019 he then had the foil put on the roof, which was his last official act. We once again had the expert come who found further defects. Among other things, the concrete walls of the overhanging basement had been chiseled back to the reinforcement so that the rebar was partially visible. In one semi-detached half, a room door was completely forgotten on the upper floor. Supporting pillars were missing, masonry was incomplete and defective, etc.
A joint site meeting between the lawyers was agreed for early January 2020. Who did not show up was the GU. His lawyer informed us that he had sold his company as of 30.12.2019 and our claims would be transferred to the successor company. As it turned out later, this was a mailbox company. He thus buried his first GmbH and we ended up with the short end of the stick.
In February, the judicial enforcement of the settlement came, awarding us €130,000, which GU1 was supposed to pay us as an advance because he had not complied with the settlement. Nice. Only that the document is now worth nothing at all.
Through our lawyer we learned that GU had already been discharged as managing director by shareholder resolution at the end of May 2019. This raises the question for me: why could he enter into a judicial settlement with us in September? Why could he issue invoices to us in October and November 2019 and sign them as managing director? After receiving this information, I reported him for fraud, but these processes are known to proceed slowly. Since the mailbox company does not exist, we now also have to pay the court’s fee assessment for enforcement.
To be continued.
Purchase of the plot in 2013
Signing of the construction contract with GU1 from the Leipzig surroundings: 16.05.2018
Semi-detached house with WU basement and finished attic
Basement: 200 sqm living space. Both semi-detached halves together just under 400 sqm
no own contributions, without painting and flooring, except tiles
guaranteed fixed lump sum price: €490,000
The plan was for my daughter and her family to move into one side of the semi-detached house and my son with his partner on the other side
In contact with GU1 since 2015, also visited several houses built by him and spoke with the builders, no major problems
Construction start: 08.10.2018
Basement excavation 1,200 m³ soil, disposal costs: €18,000 extra
later it was found that at least 500 m³ were removed unnecessarily, which were hauled back free of charge, but no reimbursement of disposal costs. It was claimed that I had wanted the removal even though I cried after every truck.
Several visits by BG Bau and imposition of a two-time construction halt because the excavation did not have the required slope, thereafter a huge construction pit was excavated, which completely sacrificed the already paid construction road.
After the completion of the ground floor (international masonry brigade without authorization for concrete and masonry work), an email arrived stating that due to static requirements, additional costs of €1,000 would be incurred. We accepted that. One day later, a new email came saying that Mr. GU had miscalculated because he forgot a beam and it was now over €6,000. We then disagreed, referring to the "guaranteed fixed lump sum price."
At the same time, it became apparent that the entire house protruded at least 12 cm higher out of the ground than planned, which was visible due to the light shafts suspended in the air, which were actually supposed to be integrated into the future parking spaces. This was initially vehemently denied. Another point was the filling and compaction of the excavation pit. According to the soil report (which the GU had), the excavation material was not suitable for refilling as it was not compactable. Nevertheless, it was used and not even compacted. This resulted in the ground giving way and the scaffolding leaning against the shell construction. Furthermore, our basement was larger than planned, which in itself would not have been bad if the ground floor above had been adjusted accordingly. The design initially did not provide for external insulation at the basement. However, at contract signing there was supposed to be 10 cm. This was apparently not passed on to the planner. Contract signing including external insulation 16.05.2018, planning documents apparently without external insulation: 18.06.2018?????
After pouring the ground floor ceiling in December, work stopped = construction stop imposed by the GU. Meanwhile, I had engaged an external construction consultant. On 17.12.2018 crisis meeting in GU’s office. At this time the invoice for the ceiling amounting to €47,500 had not been paid yet. We agreed on immediate transfer of €40,000 to the GU and withholding €7,500 until defect clarification under the condition that work would continue from calendar week 2.
Instead of continuation, all equipment and materials were removed in calendar week 2, and the scaffolding was dismantled by the end of January. The GU was unreachable. My construction consultant recommended a lawyer who then filed a lawsuit for continuation of construction in March.
In the meantime, we had commissioned an expert to determine defects, who identified defects amounting to €31,000. Thus, the GU was significantly overpaid.
From May 2018, various settlement offers went back and forth without agreement.
When in July I found out by internet research that Mr. GU had founded a second construction company, I was at my wit's end because I realized what this was heading toward. I was so desperate at some point that I called the GU’s wife (a phone number was given to me by another victim who still plays a special role here; let’s call him Mr. X) and asked her to influence her husband. She said she knew nothing about any of this. Less than 10 minutes later, I received a call from my lawyer that the GU’s lawyer had complained to him. Shortly thereafter I received a cease and desist claim and was supposed to pay €1,000. My lawyer said he could not represent me in that matter. Mr. X (as said, another victim, but not as a builder, rather as a contractor) then put me in touch with his lawyer who got me out of that situation very well.
The trial date was set for 04.10.2019. One week before, the GU entered into a settlement with us, in which we actually came out quite well. He had to pay the court and lawyer fees (totaling nearly €30,000) and damages (about €17,000). We only had to cover the settlement costs. By the settlement, he committed to completing the house by 30.11.2019. However, this date was totally unrealistic. Apart from the fact that he only resumed construction in mid-October. After the roof truss was put on (it was by then end of November and we were still miles away from completion), work stopped again.
Everything went through the lawyers again. In December 2019 he then had the foil put on the roof, which was his last official act. We once again had the expert come who found further defects. Among other things, the concrete walls of the overhanging basement had been chiseled back to the reinforcement so that the rebar was partially visible. In one semi-detached half, a room door was completely forgotten on the upper floor. Supporting pillars were missing, masonry was incomplete and defective, etc.
A joint site meeting between the lawyers was agreed for early January 2020. Who did not show up was the GU. His lawyer informed us that he had sold his company as of 30.12.2019 and our claims would be transferred to the successor company. As it turned out later, this was a mailbox company. He thus buried his first GmbH and we ended up with the short end of the stick.
In February, the judicial enforcement of the settlement came, awarding us €130,000, which GU1 was supposed to pay us as an advance because he had not complied with the settlement. Nice. Only that the document is now worth nothing at all.
Through our lawyer we learned that GU had already been discharged as managing director by shareholder resolution at the end of May 2019. This raises the question for me: why could he enter into a judicial settlement with us in September? Why could he issue invoices to us in October and November 2019 and sign them as managing director? After receiving this information, I reported him for fraud, but these processes are known to proceed slowly. Since the mailbox company does not exist, we now also have to pay the court’s fee assessment for enforcement.
To be continued.