Floor plan design single-family house (city villa 140 sqm) on a slope with double garage

  • Erstellt am 2018-07-13 11:06:26

Zaba12

2018-07-16 12:22:37
  • #1
You see. As soon as the Baukindergeld is ready to be applied for (end of August), prices will go up even faster than they have in the last 1-2 years.
 

kaho674

2018-07-16 12:26:45
  • #2
@Thies: But I haven't read anything about eaves and ridge heights anywhere either. Theoretically, couldn't you build a floor with a 10m ceiling height there, just asking stupidly?
 

Franky73

2018-07-16 13:01:17
  • #3
So now I will probably get torn apart again!

When I look on the internet, for example at Bien-Zenker, Bien-Zenker offers turnkey prefabricated houses starting at 200k, including single-story ones. Where is the catch, except that the foundation slab is not included? Of course, I understand that most fittings are just basic and that the actual final price rises again because of that. But isn't that an alternative to the planned 400k? Maybe someone can briefly explain this to me.
 

Bauprinzessin

2018-07-16 13:27:09
  • #4
Turnkey is a very flexible term. The problems are in the fine print. Just have a general contractor or Bien-Zenker or whoever plan a house according to your ideas, as some here have already told you (planning does not mean rushing to sign!). And then you should read the construction service description very carefully: what is included, what is not included, what kind of tiles, etc., electricity (number of sockets?). That means work and no one here can spoon-feed that to you. But on top of the advertised price, quite a bit is added... what about, for example, the desired garage?
 

ypg

2018-07-16 13:30:43
  • #5


What does your room program look like? I mean in writing.

Regarding your other questions or last question: the forum is full of your answers. We don’t need to repeat Adam & Eve again, you have to come up with the numbers yourself so that you get a feeling for what other things cost in turn. Or else, why this and that costs what it does.

The search function is top right. Or you open new threads. It has become completely confusing here. How are we supposed to find your site plan again?

Regarding your question: you don’t get customers if you set the price on the internet with extras that you must have or not. Then a kit home or shell house is quickly offered, which you fall for.
 

Climbee

2018-07-16 14:18:04
  • #6
I think I’ve already written here sometime that these cookie-cutter houses advertised as turnkey for under €300,000 will never be delivered for that money (or was it in another thread? Doesn’t matter). Usually, it’s not just the minimal equipment, but what’s not included:
- house connection
- toilet for the construction workers
- max. one socket in the kitchen – meaning here you will always have to upgrade if you want a house that meets modern requirements
- usually no shutters or other sun protection
- foundation slab
- development costs
- garage including foundation
- gardening work
- etc...
- and so on...

Therefore: get quotes made and compare.

And these quotes also do not include any changes that you might want (a wall added or removed, one room bigger, another smaller, windows arranged differently) or need (sloping plot!).

And these changes are then exorbitantly expensive.
 

Similar topics
08.12.2015Construction costs for KFW70 house with basement turnkey15
30.08.2012Real price for single-family house, possibly turnkey28
14.09.2012House financing - house, garage, and foundation slab approx. 290,000 EUR11
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
14.07.2015Turnkey home. Free land17
11.11.2014The Old Suffering - Turnkey/Individual Contract38
02.03.2015Turnkey house construction, but with own room layout?17
13.03.2018Turnkey Construction Land and Prices79
26.09.2016Building with an architect or turnkey14
06.10.2016Base plate with defects?22
21.11.2016Misplanning Bavaria - slope towards house and garage - instead of away23
02.09.2017Build over gas, water, electricity, and telephone lines with a garage?13
04.09.2017Sealing the garage with a concrete floor?21
03.03.2018Price difference between ground slab and basement. Can it be estimated?32
22.07.2018Detached house turnkey and garage by own effort18
10.03.2019Garage 8m x 7.5m gable roof, strip foundation, exterior plaster costs10
05.05.2020Correct execution of thermal separation house/garage16
17.08.2021Wallbox preparation garage, new construction23
24.02.2025Construction Costs Shell/Turnkey Comparison39