Regarding 1. The offer must necessarily be included. Otherwise, the application will be rejected. However, the heating system from the offer does not have to be installed later on, meaning the final invoice can differ from the offer (both the offered and the installed heating systems must be eligible for funding).

Regarding 2. Unfortunately, I do not know. When I used the Vaillant funding service, I simply provided the name of the new development area (the street did not exist yet) and the plot number. You might want to ask BAfA about this.



See above. The final invoice may differ completely from the offer submitted with the application. However, it is important that both heating systems (from the offer and final invoice) meet the funding criteria.
 

DaSch17

2020-12-07 09:44:00
  • #2


Read through my thread:

gave some valuable tips there.

Offers for air-to-water heat pump + controlled residential ventilation must then be submitted together with the application.
 

Mateo84

2020-12-07 09:57:10
  • #3
okay, but the application states the installation costs and additional costs, which must be filled out by hand.
How are these to be filled out?

My heating engineer wanted to give me a rough figure now (because it's the end of the year) and then send the concrete offer in January, so that is not possible?

Regarding deep drilling: offer available, but I can only provide the proof for the insurance once it starts, how should one deal with that?
According to the application, this must be submitted with the application?

If the heating system is allowed to deviate, I also don't understand why one has to specify the exact type there or the annual performance factor, since all that can still change, right?

best regards
 

DASI90

2020-12-07 09:57:40
  • #4


But do I then need concrete offers? From which trades, exactly?
 

Isokrates

2020-12-07 10:35:40
  • #5


Additionally:
The funding amount cannot be increased later on.
So if the actual invoice is higher than what was applied for, you only receive the applied-for amount.
 

Martial.white

2020-12-07 10:47:54
  • #6
The offers must be available to you, but they do NOT need to be submitted with the application. They must be available and if Bafa wants to see them, you have to submit them. See current screenshot from the form ...[ATTACH alt="Screenshot 2020-12-07 104615.jpg" type="full"]54459[/ATTACH]
 

Similar topics
15.06.2016Bafa: Renewable Energy Heat Pumps with Test Certification32
07.10.2016BAFA funding tips38
23.09.2017Bafa innovation funding for heat pump possibly too late - what now?15
30.09.2018BAFA funding for air-water heat pumps in new construction - how does it work?30
12.04.2019BAFA innovation funding air heat pump43
15.02.2020KFW55 funding + BAFA funding57
20.01.2020New BAFA funding - Air-to-water heat pump with solar thermal39
09.02.2020BAFA - Funding: House contract before application submission?10
27.03.2020When does BAFA pay out the funding (air-water heat pump in new construction)?10
03.06.2020KfW 55 + BAFA Funding - Costs and Subsidies24
24.05.2020Heat pump and BAFA - What is true and what is not?24
13.09.2020BAFA funding for heat pump (air-to-water heat pump) when building with a developer25
14.10.2020BU withholds "confirmation of the builder" for BAFA funding21
20.04.2021BAFA funding depends on the form "Confirmation of the Developer"20
03.01.2022Electricity meter for heat pump in combination with BAFA and photovoltaic22
17.12.2024BAFA funding - experiences with payout duration?52
01.08.2023BAFA Funding - What Waiting Time Is Realistic?27
25.04.2023Which type of funding should I choose? KfW, BAFA, tax?21

Oben