It’s getting exciting: I have actually received mail from BAFA now.
According to plan, it would have gone like this.
[*]Contract signed 11/2020
[*]BAFA application 16.12.2020
[*]Development as announced completed 01.07.2021
[*]Shortly after, construction start, let’s say 01.08.2021
[*]Construction period according to contract 8 months – turnkey handover then at the end of March 2022
By the end of March at the latest, the heat pump would have been properly put into operation if everything had gone according to plan.
What did not work:
[*]Development was not finished on 01.07.2021, but about 01.11.2021 – 4 months later
[*]Construction start was then at the end of November 2021
[*]Accordingly, per contract the house would be turnkey at the end of July 2022
[*]The fact is the house is still not finished. Tiles are currently being installed. The entire sanitary equipment as well as interior doors are still missing. However, the main point here is actually only the heat pump. There is still no sign of it at all.
To support this, I would now like to ask the municipal utilities to confirm the delay in development and ideally provide a brief explanation.
Then, and this is the difficult part, I want to get confirmation of the delay from the general contractor. I don’t yet know exactly how I will do this. The general contractor will surely not gladly write that he could not keep the construction schedule and that it will probably take much longer until the heat pump is there.
Do you have any ideas?