Bafa funding for heat pumps will be discontinued as of 31.12.2020.

  • Erstellt am 2020-12-06 12:14:12

schulan

2021-02-17 11:01:31
  • #1
Hello everyone,

I have to admit that I only skimmed through the 50 pages and did not read them in detail. Nevertheless, maybe a question (the answer to which I somewhat dread) that someone here can quickly answer.
Our construction project is being delayed quite late, possibly into next year, due to various issues. The plot has been purchased and the house contract was signed in August last year. Unfortunately, I did not apply for the BAFA heat pump subsidy in December. Is there still a possibility for a "retroactive application" since the house contract was still last year?

Additional question: Am I right in seeing that we have the worst possible subsidy starting situation? Contract signed before 2021 --> old KFW without higher repayment subsidy + missed BAFA application? :(
 

Toooias

2021-02-17 11:33:32
  • #2
You have summarized the situation well below. From everything I have read so far, the statement is unfortunately correct.
 

Baranej

2021-02-17 13:03:25
  • #3
And keep in mind that you can still secure the old KFW conditions until the end of June... otherwise, you will be left completely without funding.
 

schulan

2021-02-17 17:39:14
  • #4
Yes, unfortunately not optimal but I expected that. It's a pity. But that is what I had anticipated.


Thanks, that was not clear to me until now either. That means if it drags on until 2022 and the financing cannot be completed, I will not have the opportunity to apply for KFW :(
 

Mateo84

2021-02-17 17:43:09
  • #5
But according to the new conditions that apply from 1.7. It depends on how energetically you build. I would recommend the new one because it has more potential if you do not have the old [bafa].
 

schulan

2021-02-17 17:45:41
  • #6

Thank you for your answer. But exactly that is not possible, since the contract was signed before 01.01.2021. Otherwise, I would of course try to postpone the KFW application to 01.07. (Planned is KFW40+ including a small granny flat)
 