Construction company halts work despite overpayment

  • Erstellt am 2019-08-11 09:55:26

Hausbau2019

2019-11-15 04:08:15
  • #1
He can't do roofing, only roof trusses. According to the agreement, I am not allowed to talk to the SUBs about the construction project, only general blahblahblah..
 

Joedreck

2019-11-15 06:13:54
  • #2
Then bring the subs some coffee and cake, in the evening if they want and are allowed a beer, and sit down with them. Ask how things are going, blah blah blah.. Drop a word... Blah blah blah
 

Hausbau2019

2019-11-15 06:18:51
  • #3
They get coffee and cake with bla bla bla every day. However, the boss is informed by the [BU] and holds back a lot. He also knows what was going on with us.
 

Joedreck

2019-11-15 06:19:26
  • #4


Too bad...
 

Hausbau2019

2019-11-15 06:51:31
  • #5
It's all quite complicated. What do you say about the missing execution planning? According to the construction contract, the contractor is supposed to prepare the execution planning and coordinate it with us. We have been requesting it from him for months but have not received anything.
 

Joedreck

2019-11-15 07:09:58
  • #6
I would say that you should continue to consult with a lawyer. The whole procedure now is probably very sensitive.
 

Similar topics
29.12.2015build without execution planning if...25
05.01.2016Execution planning first agreed upon - then excluded?43
21.07.2016Execution planning, scope22
22.10.2020Building without execution planning - experiences whether this is possible?16