Since I am a bit under time pressure and have to complete my overall cost calculation by next Monday, I am bold enough to share my assumptions.
I would appreciate it if you could share your expert opinion with me - in both directions.
General construction costs
For the general construction costs, the architect and I have agreed on guideline values. He takes the entire WNFL (usable residential area) as a flat rate and calculates costs per square meter. Based on current construction costs, he speaks of €3,500 for medium to upscale standards. He would like to raise the standard to €4,000/m2 (= upscale) according to our requirements. Thus, from now on I am calculating with this guideline value for the construction costs.
Additional cost components:
That adds up to quite a lot.
Thank you very much for the input. Let me know if you think I have forgotten any important costs.
I would appreciate it if you could share your expert opinion with me - in both directions.
General construction costs
For the general construction costs, the architect and I have agreed on guideline values. He takes the entire WNFL (usable residential area) as a flat rate and calculates costs per square meter. Based on current construction costs, he speaks of €3,500 for medium to upscale standards. He would like to raise the standard to €4,000/m2 (= upscale) according to our requirements. Thus, from now on I am calculating with this guideline value for the construction costs.
Additional cost components:
[*
- Services
[LIST]
[*]Soil survey: €2,500
[*]Energy consultant: Energy Saving Ordinance certificate €1,000 plus KFW 55 approx. €1,500
[*]Fire safety consultant: €500
[*]Surveying: possibly not necessary, otherwise €1,000
[*]Architect (planning): not relevant, as already negotiated and signed
[*]Drainage plan: €2,500
[*]Demolition and clearing costs: €80,000
[*]2-3 offers will be obtained soon
[*]Kitchen with island - main house: €40,000
[*]Kitchen unit for granny flat: €10,000
[*]Photovoltaic system: €20,000
[*]Additional photovoltaic storage: €8,000
[*]Geothermal heat pump: The flat-rate construction costs already include the installation of an air-air/air-water heat pump. Therefore, I was advised to calculate with a buffer of €20,000 for the upgrade to a geothermal heat pump
[*]General ventilation system (optional) with air conditioning: €30,000
[*]Additional costs KNX: €40,000 extra costs compared to conventional electrical installation -> I will also quickly enter into discussions here
[*]Sauna: An offer of €11,000 is available -> therefore assumption €14,000 including installation
[*]Furnishing: Difficult matter. We will take furniture worth about €20,000 with us. I am currently calculating with a further €90,000 after I compiled a rough component list
[*]Garden (including terraces and driveway): €90,000
[*]Double garage: I was told €50,000 is a good estimate for a double garage. If additional space is needed for bikes, etc., I should add 50% area, so €75,000
[*]Optional: Pool (either 3.5 x 8 m or 3.5 x 10-12 m) including heat pump and counter-current system: €100,000
That adds up to quite a lot.
Thank you very much for the input. Let me know if you think I have forgotten any important costs.