Ceiling is installed and ventilation ducts are laid. Concrete is scheduled for Wednesday. The 5 openings for the water and sewage pipes are to be created later by the construction company using core drilling.
As a construction layman, this can quickly happen. Which is not bad,
Do you mean hegi by laymen? Our architect, for example, placed a light well directly at the terrace exit... At the neighbor's, the architect planned the stairwell so small that the glass did not fit, etc.
In the meantime, planning for the next project begins: €1200/m2 multi-family house. The old shack is to be demolished and replaced by a flat-roofed house with 3 full floors. 5 residential units
I find your posts very interesting! I will follow how it continues! For us, everyone finds 470k without land not feasible here despite countless planned own contributions
So I can only advise you to get quotes as early as possible with drawings, sketches, or self-made plans. And at least 3-5 per trade. That way you get a good overview. Also about the material that you install yourself.
The prices I found on the internet did not match my own at all. And the quote prices always fluctuate by about +-50%.