SSchimi1791 2020-12-05 19:46:40#1Do you put the drywall directly on the vapor barrier/vapor retarder? In our case, it looked like this:
Do you put the drywall directly on the vapor barrier/vapor retarder? In our case, it looked like this:
Hhegi___ 2020-12-06 06:34:29#2 Do you install the drywall directly onto the vapor barrier/-retarder? In our case, it looked like this: No, two rows of profiles are installed first, then drywall
Do you install the drywall directly onto the vapor barrier/-retarder? In our case, it looked like this: No, two rows of profiles are installed first, then drywall
Hhegi___ 2020-12-18 08:58:19#3Plaster on the outside and inside is done, and the access path is gravelled. The plaster has cost me 20k now, and the company was really great.
Plaster on the outside and inside is done, and the access path is gravelled. The plaster has cost me 20k now, and the company was really great.
Kknalltüte 2020-12-18 11:04:40#4Hi, cleaning for 20K is probably a fair price if done well. But tell me, what kind of "cat flap" is that under the window (middle picture)?
Hi, cleaning for 20K is probably a fair price if done well. But tell me, what kind of "cat flap" is that under the window (middle picture)?
Hhegi___ 2020-12-18 11:17:15#5 Hi, plastering for 20K is probably a fair price if done well. But tell me, what kind of "cat flap" is that under the window (middle picture)? :D Yes, a bigger door would have looked better in hindsight.
Hi, plastering for 20K is probably a fair price if done well. But tell me, what kind of "cat flap" is that under the window (middle picture)? :D Yes, a bigger door would have looked better in hindsight.
Hhegi___ 2021-01-02 14:56:10#6Underfloor heating is installed. Budget 262 / 300k spent. On Monday, I will be informed when the liquid screed can be installed. After that, there is a 6-week drying period during which I will complete the ventilation system. The planned move-in date is April 1st.
Underfloor heating is installed. Budget 262 / 300k spent. On Monday, I will be informed when the liquid screed can be installed. After that, there is a 6-week drying period during which I will complete the ventilation system. The planned move-in date is April 1st.