Construction report single-family house 1200 €/m²

  • Erstellt am 2020-06-14 12:05:45

Winniefred

2020-10-13 15:08:38
  • #1
What does this mean concretely for you in the coming months?
 

11ant

2020-10-13 15:17:33
  • #2

To me, this rather sounds like a risk in the form of ten percent of unpaid work that the insolvency administrator can still claim. The phase between the insolvency filing and the appointment of the administrator is unfortunately invisible in the commercial register. Especially in the case of an external application, the examiner will usually also investigate whether there are indications of delay suspicion. The popular misconception that an insolvency merely removes one player from the board can catch you off guard.
 

face26

2020-10-13 15:23:49
  • #3


I really feel sorry for you, no one deserves that. It will probably be rather difficult to hope for any corrections of defects, let alone any warranty.

Keeping my fingers crossed that you find someone who will complete the remaining 5%!
 

ypg

2020-10-13 15:29:16
  • #4


Sorry for barging into the thread. I haven't been following here. As soon as you do, you read that the 1200€/sqm house construction is not going as planned after all.
I wish you good luck! Even if it probably won’t stay at 1200€ after all?!?!
 

haydee

2020-10-13 15:48:53
  • #5
I would have the defects recorded by an expert and submit the report. Maybe you have a chance to withhold the costs for the rework. I fear otherwise you will pay the 10% plus the rework.

Fingers crossed that you find a company that continues promptly
 

hegi___

2020-10-13 15:58:07
  • #6
Of course, I was already expecting that.... The defects are nothing major overall and there are still 15k left. That should be enough for me to do the infilling of the rafters, ring beams in the gables, and the remaining interior walls on the upper floor. There should also be enough bricks left.
 

Similar topics
10.08.2018Landscaping company - defects, high bill, no warranty?!13
18.10.2018Liability for various defects after acceptance of the property19
21.05.2019Balcony door and window sills - defects in new construction28
21.05.2019Water connection installed incorrectly - Right to correction from the general contractor?39
09.03.2021Withholding payment for defects in the shell construction74
24.12.2021GU insolvency after acceptance - Open defects15
03.10.2022Building acceptance of new construction despite missing heat pump. Significant defects?50
26.07.2023Very messy parquet laying work - Is rework not possible?113
06.04.2023Deficiencies in the new construction. Dispute over the amount of withholdings.35
19.04.2024Bank withdraws financing commitment due to defects20

Oben