After almost 3 weeks, the foundation slab was actually supposed to be concreted today. However, this morning I received an email that the building materials supplier postponed the concrete delivery. The reason is that the construction company has apparently overdrawn their account due to excessive material orders.
I had already received the first partial payment of 20k last week, which of course I have not yet paid. (this includes 7k material advance for stones)
I have now had the concrete delivery invoiced to my account at the building materials supplier, so it will continue tomorrow.
As compensation for the delays, the construction company has now offered me a discount on the total amount. (1800 euros)
The construction company has also acknowledged the non-payment of the partial payment. However, today I only released the prefabricated staircase, so we still do not have an appointment for the filigree ceiling. The delivery time currently is between 6-8 weeks everywhere for us.
Since I am realistic and cannot expect cheap + quality + speed, I am still more or less relaxed about it.
However, the stones are supposed to be delivered this week.