Such a thing does not exist because too many factors can influence the schedule.
Now it is time to create a project that you like. Then follows the preparation of the building application. That takes about 3 months.
During this time there is time for the selection of materials. Roof tiles, window colors, doors, tiles, sanitary fittings, etc. The additional cost must then be taken into account. However, it is not counted as part of the ancillary building costs.
That is why you build a buffer into the financing. For example, 15000. This compensates for the selection of materials and additional costs.
You can also first do the selection of materials and then create financing with the total amount.
Determination of the ancillary building costs and costs for the outdoor facilities is done by you or the financial advisor. Often the house building company can also help to estimate.
Normally with us here it is about 20000 each. If you have to do a clearing and forest conversion you should add amount X.
But there will be no schedule for that. It only exists when the financing is in place and the building application is approved.
Electricity and water must be available. Then there is a plan for when it starts and a chronological sequence.