...by the way, a calculation for the bank is _not_ detailed.
For example, ancillary building costs: 40000! Not: earthworks 10000, developer 8999, permits 2000, etc.
Outdoor facilities 15000! Not: paving work 10000, hedge 2000, carport 4000, etc.
House including special equipment 300000! Not: fireplace 10000, platform 1000, electrical 5000...
It is normally divided into:
house costs
special equipment
ancillary building costs
outdoor facilities
miscellaneous and EL
buffer
Regards