Floor plan design for a hillside house with 5 children's rooms

  • Erstellt am 2017-06-17 12:31:53

Arifas

2018-02-12 19:42:00
  • #1
Today we spoke with the earthworks contractor. On Saturday we will meet at the property; at the beginning of March it starts [emoji898][emoji445]

And we have ordered a fireplace and are super excited [emoji7]. It will be installed in the front left corner when viewed from the front. Built mirror-inverted
 

Arifas

2018-02-14 19:28:45
  • #2
We have completed the workshop planning meeting, been assigned a site manager, and with a bit of luck the construction start meeting will take place next week [emoji445][emoji126].

We were very pleased that we were able to move the sink in the parents' bathroom to the wall where the radiator is marked on the plan. These two simply swap places now, and as a result, we can even install our 1m wide washbasin. The air-to-water heat pump is now moving to the front of the house and thus away from the bedroom window.
The kitchen will get a window to the left of the sink, and we have discussed all the rooms with the electrician. Adjusted pricing from the electrician was already in the inbox this evening.

There seems to be a surprise with the earthworks, but we will only see that at the end of the week...
 

haydee

2018-02-14 19:32:03
  • #3
Then I am soon looking forward to photos.

Hopefully a good surprise
 

Arifas

2018-02-14 19:47:46
  • #4
That will still prove itself [emoji85][emoji23].

Our shell builder is now confirmed and, for warranty reasons (earth-contact exterior wall, backfilling, etc.), prefers to carry out the earthworks himself. That’s what we wanted from the beginning. It was always said that we absolutely have to find an earthworker ourselves, which we have finally managed to do. And regarding coordination on the construction site, the site manager now also strongly recommends working with the shell builder.

I have been completely transparent with our really very nice earthworker we found ourselves. He is a) currently not very well health-wise and b) he clearly advises us to go with the shell builder as the earthworker. I find that very kind and generous, after all he is missing out on a comprehensive job. We highly appreciate that he gave us this feedback directly (in writing) and would definitely compensate him for preparing the offer in this case.

But now we will first wait for the shell builder’s offer and take it from there. We’re already a bit under pressure because the shell builder is basically resisting a bit if he doesn’t do the earthworks and backfilling... Let’s see how things develop.
 

haydee

2018-02-14 23:28:48
  • #5
Is it normal here that the person who builds the retaining walls also fills them up.

Do you have a lot of excavated material?
 

Arifas

2018-02-15 10:59:10
  • #6
It’s probably better that way. We wanted it like that from the beginning. They always said they don’t offer that. Well. Now they do after all.

We will have about 350 cubic meters to dispose of
 

Similar topics
09.06.2013Costs of earthworks without basement15
22.08.2013Are the estimated costs of the general contractor for earthworks reasonable?12
07.03.2014Earthworks are starting, but I need a tip.12
26.04.2016Sand, gravel, and other earthworks32
28.09.2016Evaluation of earthworks offer14
28.08.2017Earthworks: Making the right choice of provider14
29.12.2017Is it possible to found a single-family house without concrete and earthworks?21
25.01.2018Earthworks and shell construction, who bears the warranties?10
10.07.2018Does the structural builder have to paint the transition between styrofoam and brick wall black?12
15.10.2018Is the shell construction overloaded? Current situation in the construction industry!13
08.11.2018Structural shell / Structural shell cost calculation - How does it calculate?52
29.10.2018Earthworks in the construction performance description17
08.04.2019Earthworks costs in Bavaria15
14.06.2019Costs for earthworks18
20.02.2020What does the electrician do during the shell construction phase?19
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
08.09.2020Earthworks costs, hillside house14
21.07.2021Problem with the electrician - what would you do?78
23.07.2021Earthworks... Dispute with the occupational disability insurance20
27.11.2021Ancillary construction costs for earthworks according to soil report16

Oben