DaSch17
2020-07-29 10:06:59
- #1
Hello dear community,
we have revised our budgeting based on the current floor plan (#145). Could you please take a look and see if the calculation is okay and somewhat realistic:

We have included various buffers here, some of which can be found in the position "buffer" and some have been generously calculated: 1.) Land: In the adjacent new development area, the plots were last sold by the municipality for 75 EUR/m². According to the municipality, they also want to offer at this price in the new development area. Nevertheless, we preferred to calculate with 90 EUR/m²: buffer = 11.5 TEUR 2.) Foundation: Cost estimate from the house builders (each independently): approx. 30 TEUR; we have additionally included a 10 TEUR buffer here (high groundwater level, clay soil (poor rainwater infiltration), and height difference of 2.5m on the plot)
This results in a total reserve of 52.5 TEUR.
We have determined the self-performed work as follows:

Initially, we calculated completely without external help, but only with our already accrued vacation days.
Do you think this is about right or is it total nonsense?
we have revised our budgeting based on the current floor plan (#145). Could you please take a look and see if the calculation is okay and somewhat realistic:
We have included various buffers here, some of which can be found in the position "buffer" and some have been generously calculated: 1.) Land: In the adjacent new development area, the plots were last sold by the municipality for 75 EUR/m². According to the municipality, they also want to offer at this price in the new development area. Nevertheless, we preferred to calculate with 90 EUR/m²: buffer = 11.5 TEUR 2.) Foundation: Cost estimate from the house builders (each independently): approx. 30 TEUR; we have additionally included a 10 TEUR buffer here (high groundwater level, clay soil (poor rainwater infiltration), and height difference of 2.5m on the plot)
This results in a total reserve of 52.5 TEUR.
We have determined the self-performed work as follows:
Initially, we calculated completely without external help, but only with our already accrued vacation days.
Do you think this is about right or is it total nonsense?