Hello everyone,
after the discussion in thread about our construction financing and after receiving many good tips, I would like to present our construction costs so far. I found it incredibly helpful at the beginning of our project to see what items to expect and roughly what costs to anticipate. Below are some current figures from autumn 2020. Maybe it will help one or the other interested reader as well.
For context: The following information comes without guarantee :) and is of course relative and depends on the construction site. We are building a single-family house with an architect, flat roof, 193 sqm, garage for one car, and to the KfW40+ standard. Most items are backed by quotes, others already paid, and some are estimates. The first three tables are certainly relatively generally valid, as they are independent of the budget. The tables regarding the house naturally depend on the house and the chosen standard.
Here are the items for our plot:
[TH]Item Land Purchase[/TH] [TH]Costs (rounded)[/TH]
|
|
Status inquiry biotope as the plot was heavily overgrown being a neglected garden |
102 € |
Notary purchase contract |
1,350 € |
Land register fees for land charge pre-notation |
215 € |
Broker commission including deposit |
11,400 € |
Fee negative certificate municipality xxx |
45 € |
Purchase price plot 884 sqm |
170,000 € |
Share surveying plot for subdivision |
1,560 € |
Real estate transfer tax (6.5% purchase price) |
11,060 € |
We bought the rearmost piece of a subdivided plot, which was not only almost 75 meters away from the street but also a complete jungle. Additionally, we had to participate in the demolition costs of a house on subdivision plot 1 as per contract. The costs for development (here we partly shared costs with our neighbor), clearing the plot, and a construction road (it should be noted that we have to keep part of the road as a fire department parking area - this part, however, is on the neighbor's plot) are as follows:
[TH]Item Development and Construction Preparation[/TH] [TH]Costs (rounded)[/TH]
|
|
Cadastral office |
220 € |
Soil survey |
790 € |
Share demolition of a single-family house with basement, shed, and garage (1/3) |
10,000 € |
Surveyor creation of site plan |
1,690 € |
Notary |
230 € |
Real estate transfer tax additional payment on surveying and demolition costs |
754 € |
Basic fee land charge |
415 € |
Fees for encumbrances for two plots in front of us |
800 € |
Connection fees electricity from street to plot (75 meters) without earthworks |
3,250 € |
Sewage-water channels, empty conduits for electricity, telecom share (2/3 for about 70 meters) as well as share of construction road made of natural gravel |
9,560 € |
Fees associations, house number, etc. |
300 € |
Connection fees water |
1,500 € |
Connection fees sewage |
2,400 € |
Clearing of plot and tree cutting |
3,800 € |
Surveyor surveying |
1,400 € |
Notary registration of land charge |
4,000 € cost estimate |
For the house planning, the following items have been incurred so far, with the architect's costs not being representative due to acquaintance:
[TH]Item House Planning[/TH] [TH]Costs (rounded)[/TH]
|
|
Architect service phases 1-4 |
8,500 € |
Energy consultant |
1,120 € |
Statics |
7,500 € |
Fees building application |
1,500 € |
Architect costs service phases 4-5 |
22,000 € |
Now it’s finally starting. Below are costs for the house, although some estimates are still included.
[TH]Item House Construction Building[/TH] [TH]Costs (rounded)[/TH]
|
|
Batter board, cistern |
5,000 € |
Earthworks and base pipes |
8,000 € |
Base slab + strip foundations |
26,000 € |
Concrete and steel works including concrete pedestal stairs |
45,000 € |
Wall and masonry works |
43,000 € |
External cladding and plaster layer |
40,000 € |
Room-side plaster layers Q2-Q3 including white exposed plaster inside in sqm |
22,500 € |
Sealing and screed |
5,000 € |
Flat roof construction including 20 cm insulation + frame cladding aluminum or zinc |
30,000 € |
Dry construction |
2,500 € cost estimate |
Room-side paint inside in sqm |
10,000 € cost estimate |
Stoneware tiles parents' and children's bathroom including walls + guest WC, about 55 sqm |
6,000 € |
Exposed screed utility room, pantry, kitchen, hallway, guest WC, about 50 sqm |
5,000 € |
Parquet, about 120 sqm |
15,000 € cost estimate based on initial offers |
15 x windows (aluminum or wood-aluminum) with blinds and south-facing with venetian blinds, partly special sizes, floor level, etc. |
55,000 € |
Front door |
5,000 € |
Garage door |
4,000 € |
2 x sliding doors + 2 x security doors garage and pantry |
5,000 € |
9 x solid wood interior doors |
6,000 € |
I am currently still waiting for two quotes for the items with asterisks. It can certainly be cheaper. However, the BAFA subsidy must also be factored in, so it will be more moderate again.
[TH]Item House Construction Technology[/TH] [TH]Costs (rounded)[/TH]
|
|
House connection telecom, electricity, water and sewage from plot boundary to house |
5,300 € cost estimate |
Pipes hot and cold water in m * |
7,100 € |
Air heat pump with 300 L hot water storage including installation (model not final yet, probably one from Viessmann or Wolf) * |
16,000 € (BAFA eligible) |
Underfloor heating in sqm, with insulation without heated screed * |
11,000 € |
Central ventilation system * |
15,400 € (BAFA eligible) |
Water softening system * |
2,000 € |
Sanitary fixtures (to be purchased separately) |
14,000 € cost estimate |
Photovoltaic 9.6 kWp + battery 11 kWh including installation |
22,000 € |
Electrical installation, cables, sub-distributors, sockets, lightning protection, no/almost no automation |
18,000 € |
Lighting planner and lighting |
10,000 € |
For kitchen and garden, we have each reserved about 20k. But there is nothing concrete yet. These are our numbers so far.
If you have any questions, feel free to let me know. Otherwise, thanks to this forum, which has helped me in many ways.