Aloha_Lars
2022-08-08 12:25:39
- #1
at my house. Start of the earthworks. After the geo report it turned out that there used to be a gravel pit there. Additional costs for necessary well rings +60000€. Disposal of hazardous waste at landfill +35000€. Additional costs for thicker necessary base slab +17000€. More steel, better steel, etc. +10000€. Additional costs only for the earthworks. Things like this add up quickly,
Why does someone in Germany always think that individual cases must be generalized to the whole population?